Standard Specifications for Highway Construction, January 1, 1968 |
From inside the book
Results 1-3 of 8
Page 501
... sodded and mulched as required , without unnecessary delay and before undesirable weed growth or soil erosion occurs . If any of the work provided for herein is performed under unfavorable conditions or contrary to the restrictions and ...
... sodded and mulched as required , without unnecessary delay and before undesirable weed growth or soil erosion occurs . If any of the work provided for herein is performed under unfavorable conditions or contrary to the restrictions and ...
Page 508
... sodding , jute fabric , or grading , that would in any way prevent or minimize the possibilities for erosion within a particular drainage area upon its completion . Acceptance of seeding will be made in writing by the Engineer , after ...
... sodding , jute fabric , or grading , that would in any way prevent or minimize the possibilities for erosion within a particular drainage area upon its completion . Acceptance of seeding will be made in writing by the Engineer , after ...
Page 510
... Sodding Sodding will be measured by the area sodded and accepted , based on actual measurements taken along the surface of the sod , except that the width measurement on areas covered in uniform strips may be considered as the product ...
... Sodding Sodding will be measured by the area sodded and accepted , based on actual measurements taken along the surface of the sod , except that the width measurement on areas covered in uniform strips may be considered as the product ...
Contents
GENERAL REQUIREMENTS AND COVENANTS | 1 |
Bidding Requirements and Conditions | 11 |
Award of Contract | 17 |
2 other sections not shown
Common terms and phrases
AASHO acceptable accordance additional aggregate Aluminum applied approved Asphalt Asphaltic Concrete backfill base BASIS OF PAYMENT batch bituminous material bolts bridge calcium chloride casting cement cent coat cofferdam compacted compensation in full completed concrete conform Contract prices Contractor Cubic Yard culvert curing designated diameter dimensions embankment Engineer equipment excavation fabric falsework feet finished fog seal furnished galvanized girders grade haul holes inch inspection installed Item joints length less Linear Foot locations measured ment metal method minimum mixer mixing mixture mulch operations paint pavement permitted piles pipe placed placement Plans plant plates portland cement posts pounds prior Project quantity removed requirements of ASTM riprap rivets road Road Tar Roadbed roller SAMPLING AND TESTING SCOPE This Specification screed seal shown sieve Sieve Analysis soil Specification covers strength Structural Steel Subgrade surface temperature thickness timber tion traffic unit wearing course weight welding width wire