Page 97 - ... that the said work, or any part thereof, Is unnecessarily or unreasonably delayed, or that the Contractor is...
Page 26 - ... stock and bonds, or the proceeds thereof, to be applied to the following purposes and to no other, to wit...
Page 84 - ... or any part thereof, and in case such expense is less than the sum which would have been payable under this contract, if the same had been completed by said contractor, then the said party of the second part shall be entitled to receive the difference...
Page 97 - In all operations connected with the work, the contractor shall comply with all laws or regulations affecting in any way the conduct of those engaged on the work, or the methods of doing the work, and persons employed in the performance of manual labor under this contract shall not be required to work more than nine hours in each day, and said nine hours shall constitute a day's work...
Page 101 - Lessor the said yearly rent, upon the days hereinbefore appointed for the payment thereof, and also all the taxes, water rates and assessments whatsoever, whether in the nature of taxes now in being or not, which may be payable for or in respect of the said premises, or any part thereof during said term...
Page 97 - Contractor shall take all responsibility of the work, and take all precautions for preventing injuries to persons or property in or about the work ; shall bear all losses resulting to him on account of the amount or character of the work, or because the nature of the land in or on which the work is done is different from what was estimated or expected, or on account of the weather, tides, elements, or other cause.
Page 83 - ... contract rates for work of similar character; or, if the extra work should be of a class for which no rate is fixed by current contracts, the actual reasonable cost to the contractor as determined by the engineer, plus 15 per cent. The contractor shall have no claim for compensation for extra work unless the same is ordered in writing by the engineer.
Page 77 - Charlestown, all the work to be done and completed in the manner and in accordance with and subject to the terms and conditions set forth in the following specifications. The word
Page 101 - And the said party of the second part further covenants that he will not assign this lease, nor let or underlet the whole or any part of the said premises, nor make any alteration therein, without the written consent of the said party of the first part, under the penalty of forfeiture and damages...
Page 83 - Board before the fifteenth day of the month following that during which each specific order is complied with. Convenient facilities for the inspection of the work shall be furnished by the Contractor whenever requested by the Engineer. All instructions and directions of the Engineer to be strictly observed and followed, and when the Contractor is not present to receive them, they shall be received and obeyed by the superintendent or foreman who may have charge of that particular work in reference...