Critical Path Analysis: Problems and Solutions |
From inside the book
Results 1-3 of 8
Page 53
... wharves at a suitable North London depot . From these wharves , British Railways ' vans will distribute to the London shops . It is expected that both the sidings and the wharves will need to be modified in order that the goods can be ...
... wharves at a suitable North London depot . From these wharves , British Railways ' vans will distribute to the London shops . It is expected that both the sidings and the wharves will need to be modified in order that the goods can be ...
Page 54
... wharves Obtain estimate for modification to wharves Agree estimate for modification to wharves Modify wharves 15 days 15 days 4 days 14 days 7 days 7 days 15 days British Railways obtain sample container 7 days Arrange test run from ...
... wharves Obtain estimate for modification to wharves Agree estimate for modification to wharves Modify wharves 15 days 15 days 4 days 14 days 7 days 7 days 15 days British Railways obtain sample container 7 days Arrange test run from ...
Page 115
... Wharves Survey for Modifications Wharves 7 14 Agree Estimates for Modifications to Wharves 7 27 7 Sign Contract to Modify Wharves 3 Train Modify Wharves Wharf Staffs 35 41 15 3 14 Production Obtain Production Make Make Samples 15 ...
... Wharves Survey for Modifications Wharves 7 14 Agree Estimates for Modifications to Wharves 7 27 7 Sign Contract to Modify Wharves 3 Train Modify Wharves Wharf Staffs 35 41 15 3 14 Production Obtain Production Make Make Samples 15 ...
Other editions - View all
Common terms and phrases
Activities Involved ACTIVITY START FINISH adhesive tape Agree sales analyse the network anodizing Approach Road Signs arrow diagram Assemble Complete Equipment bar chart British Railways burglar alarm compressor cost-slope Critical Path Analysis cure day Inspect days Obtain deliver console depends on tasks Design tower Dispatch Draw the network Dummy Duration E L Erect final assembly FINAL TEST GEAR FINISH FLOAT Numbers finishing date FLOAT Numbers Description FLOAT Numbers Duration free float increase insp Install Machine lagging lifting gear mainlaying manufacture Mechanical proving tests Number of Operators Numbers Description Duration Obtain and Install office island Order console petrol station pipe pipe-work and tanks PPMs Prepare Advertising production equipment Raise purchase Raw material Rubble Fill sales island base sample heaters second assembly second machine Sell-in shuttering Storage Heater Task K depends Test component Test Gear 20 test run third machine Total Free Ind total project weeks 1 week weeks Obtain wharves