... DAILY OUTPUT COLUMN To the right of every crew code listing in the Unit Price section , a Daily Output figure is given . This figure represents the number of units that the crew listed for that line item will install in an 8 - hour day ...
... DAILY OUTPUT COLUMN To the right of every crew code listing in the Unit Price section , a Daily Output figure is given . This figure represents the number of units that the crew listed for that line item will install in an 8 - hour day ...
Page x
... Daily Output This is the number of units that a given crew will install in an 8 hour day . In other words , the total daily crew cost divided by the Daily Output will produce the unit installation cost . To calculate the unit equipment ...
... Daily Output This is the number of units that a given crew will install in an 8 hour day . In other words , the total daily crew cost divided by the Daily Output will produce the unit installation cost . To calculate the unit equipment ...
Page 190
... DAILY MAN- BARE COSTS odiloniM 03Y TOTAL CREW OUTPUT HOURS UNIT MAT . LABOR EQUIP . TOTAL INCL . O & P 050 CERAMIC TILE 0020 3000 3100 Floors , natural clay , random or uniform , thin set , color group 1 Color group 2 D - 7 183 .087 ...
... DAILY MAN- BARE COSTS odiloniM 03Y TOTAL CREW OUTPUT HOURS UNIT MAT . LABOR EQUIP . TOTAL INCL . O & P 050 CERAMIC TILE 0020 3000 3100 Floors , natural clay , random or uniform , thin set , color group 1 Color group 2 D - 7 183 .087 ...
Other editions - View all
Common terms and phrases
aluminum average backfill backhoe Bare Costs Incl Bituminous brick Building Laborer 15.50 C.Y. bucket C.Y. dump trailers C.Y. dump trucks Carp cement Clab coat Common earth compaction concrete construction COST PER L.F. Cost Per Man-hour Costs Incl crane CREW OUTPUT HOURS Cubic Yards Daily Bare Costs Daily Hr Daily Totals deep diameter B-20 dozer end bearing estimating Expanded System Listing Fiberglass finish frame Friction type gallons galv gravel base haul Height above grade HOURS UNIT MAT HP dozer INST Installation KSF soil capacity LABOR EQUIP Labor Foreman lifts load loader long wing walls material mile round trip minimum Maximum Oper OUTPUT HOURS UNIT pile cluster Plum plywood Polyethylene Polyethylene pipe precast pump PVC pipe QUANTITY UNIT MAT reinf reinforcing risers Slab on grade steel Subs O&P Cost System Listing shows thick track loader trench Unit Price wellpoint wide wood