Means Interior Cost DataLabor & materials costs for interior items for construction cost estimators. |
From inside the book
Results 1-3 of 79
Page 339
... Installation ( 333.75 ) Installation includes labor and equipment plus the installing contractor's overhead and profit . Equipment costs are the bare rental costs plus 10 % for profit . The labor overhead and profit is defined on the ...
... Installation ( 333.75 ) Installation includes labor and equipment plus the installing contractor's overhead and profit . Equipment costs are the bare rental costs plus 10 % for profit . The labor overhead and profit is defined on the ...
Page 497
... installation or post - installation ? Change order work costs vary according to how much of the installation has been completed . Once workers have the project scoped in their mind , even though they have not started , it can be ...
... installation or post - installation ? Change order work costs vary according to how much of the installation has been completed . Once workers have the project scoped in their mind , even though they have not started , it can be ...
Page 498
... installation into a new weather season . For example , underground piping scheduled for October installation was delayed until January . As a result , frost penetrated the trench area , thereby changing the degree of difficulty of the ...
... installation into a new weather season . For example , underground piping scheduled for October installation was delayed until January . As a result , frost penetrated the trench area , thereby changing the degree of difficulty of the ...
Other editions - View all
Common terms and phrases
1999 BARE COSTS 9 FINISHES aluminum BARE COSTS TOTAL Bare Incl block brick brushwork butt welded 8-3/4 Carp ceiling Clab coat Cost Data COST PER S.F. COSTS TOTAL CREW COSTS TOTAL MAT crane CREW OUTPUT HOURS Daily Costs O&P Daily Hr DAILY LABOR Daily Totals deep diam diameter DOORS & WINDOWS drywall K.D. Elec EMT & wire estimating exterior latex fiberglass fixtures FLOORING & CARPET frame galvanized glazed GYPSUM BOARD HOURS UNIT 1999 HOURS UNIT MAT included INST installation Interior iron pipe iron pipe size LABOR EQUIP Labor Foreman Labor-Hour latex LATH MASONRY Metal minimum Maximum MOISTURE PROTECTION mounted Oper OUTPUT HOURS UNIT panels PLASTER & GYPSUM Pneumatic nailed Pord primer QUANTITY UNIT MAT risers rough-in Stainless steel THERMAL & MOISTURE thick tile TOTAL CREW OUTPUT TOTAL INCL 0&P TREATMENT & WOOD Truck type NM cable Vinyl WALL COVERINGS watt wide WOOD & PLASTICS